Federal Appeals Court Tosses Permit for Atlantic Coast Pipeline Station
1/7/2020 Source: AP RICHMOND, Va. (AP) — A federal appeals court has thrown out a permit needed by developers of the Atlantic Coast Pipeline to build […]
Read more1/7/2020 Source: AP RICHMOND, Va. (AP) — A federal appeals court has thrown out a permit needed by developers of the Atlantic Coast Pipeline to build […]
Read more“All of these agencies agree that the Forest Service has the full legal authority to approve the Atlantic Coast Pipeline’s crossing of the Appalachian Trail,”
Read more1/31/2019 Reuters – A U.S. appeals court has stayed a previous court decision against Forest Service permits that allowed Dominion Energy to build the $7 billion […]
Read moreBy Gregory S. Schneider October 20 RICHMOND — Virginia regulators say they have cleared the controversial Atlantic Coast Pipeline to begin construction on its 300-mile track across the […]
Read moreRICHMOND, Va. (AP) – Federal officials will allow construction to resume on the Atlantic Coast pipeline, weeks after work was halted when a federal appeals court […]
Read moreRALEIGH, N.C. (AP) — The Federal Energy Regulatory Commission has approved construction of the 600-mile Atlantic Coast Pipeline to proceed in North Carolina. FERC officials this week […]
Read moreThese four crafts and trades will include a mix of local and non-local workers.